Gymnasium, Bösingen FR

2014

On behalf of the municipality of Bösingen, Timbatec AG carried out an expertise on the roof of the gymnasium. It showed that the structural safety of the supporting structure was no longer guaranteed.

Facts and images
Construction Data
Involved
Interior view ceiling
Interior view ceiling
Interior view ceiling
Interior view ceiling
Interior view of the hall
Interior view of the hall
Old and new truss
Old and new truss
Roof rack
Roof rack

The project
The initial situation After the expert report had been submitted, the hall had to be closed immediately because the structural safety of the supporting structure was no longer guaranteed. The gusset plate trusses were too weakly dimensioned for the latest generation of standards and had to be replaced.

The construction
Strengthening the old supporting structure was out of the question for cost reasons. The municipality therefore decided not to renovate the old roof but to replace it.

The challenge
Since the gymnasium is directly adjacent to the community center, the external appearance could not be changed. The new supporting structure was built with trusses that span the width of the hall at intervals of 4.5 meters.

Construction Data

- Trusses


Services of Timbatec

- SIA phase 31 preliminary project

- Cost estimate

- SIA Phase 32 Construction project

- Structural analysis and design

- SIA Phase 41 Tendering and comparison of offers

- SIA Phase 51 Implementation project

- Site supervision and site inspections

Timber construction contractor
Beer Holzbau AG
3072 Ostermundigen


Architect
Atelier 99 AG
3178 Bösingen


Building owner
Residents' municipality of Bösingen
3178 Bösingen


Timber construction engineers
Timbatec Holzbauingenieure Schweiz AG, Thun
3600 Thun