The project
In this conversion, architect Beat Nievergelt rethought the house and gave the small-scale apartments a sense of spaciousness and a sense of the outside. This required a considerable intervention in the primary structure: the load-bearing corridor walls were partially removed with a view to the new spatial structure; their load-bearing function was taken over by columns and beams. The wooden beams of the ceiling were exposed and replaced where necessary, their interstices filled with lightweight concrete and straightened in level. A suspended plaster ceiling and rock wool help to comply with the limits for impact sound.

The construction
The addition is a wooden element structure built on top of the exterior walls and provides space for a maisonette apartment. Its false ceiling is suspended from the roof beams with tie rods. The partially exposed wooden beams and braces remain visible and have been skillfully integrated into the apartments.

The challenge
The rafter layer with a knee wall rests directly on the joist layer. Due to the asymmetrical construction method, flexurally rigid connections between the rafter layer and the knee wall were required. The floor slab with the very large span is cantilevered and also serves as a hatch. It was suspended from the center purlin with tie rods.

Construction Data

- Land area 119 m2

- Floor area total 629 m2


Construction costs

- BKP 1-9: CHF 1'909'000.-

- BKP 2: CHF 1'860'000.-


Services of Timbatec

- SIA Phase 11 Condition analysis

- SIA Phase 21 Structural analysis

- SIA Phase 32 Construction project

- SIA Phase 41 Tendering and comparison of offers

- SIA Phase 52 Execution

Architect
Beat Nievergelt GmbH 8032 Zurich


Timber engineer
Timbatec Holzbauingenieure Schweiz AG 8005 Zurich


Civil engineer
Tragwerkstatt GmbH 8006 Zurich


Building physics
aundb bauphysik gmbh 8400 Winterthur


Photography
Andrea Diglas Photography



Datenschutzhinweis

Diese Webseite nutzt externe Komponenten welche dazu genutzt werden können, Daten über Ihr Verhalten zu sammeln.

Notwendige Cookies werden immer geladen