Refurbishment multi-purpose hall HUM2, Payern

2022

In the 1970s, the army had a great need for new multi-purpose buildings and had two types of halls developed for this purpose. These buildings are getting on in years and are being renovated and strengthened against earthquakes.

Facts and images
Construction Data
Involved
Gymnasium before renovation
Gymnasium before renovation
Gymnasium after renovation
Gymnasium after renovation
Interior view after renovation
Interior view after renovation
Construction detail facade
Construction detail facade

The project 

Today, the real estate portfolio of armasuisse Immobilien includes 30 multi-purpose halls of type 71 and seven halls of type 76. These multi-purpose halls were built between 1969 and 1992 and in some cases show signs of age which now have to be renovated. A baseline report shows that various halls no longer meet today's specifications for earthquake safety. In the course of the renovation work, the halls will be structurally strengthened. The weapons range in Payerne has several multi-purpose halls. A complete renovation was planned by Haller Gut Architekten AG in 2016. Timbatec was allowed to accompany this renovation as a timber construction engineer and was able to apply its experience to the renovation of the second multi-purpose hall on the same armoury.

The construction method 

The infill panels between the steel frames were removed and replaced by prefabricated wooden elements. They stiffen the hall so that it meets today's static requirements. On the inside, the steel girders remain visible, which shapes the hall space through the grid of filigree steel frames. This is how all the elements were planned around the existing steel frame. The outer façade is characterised by the vertically mounted wooden formwork. 

The challenge 

The wall panels as well as the roof were made of prefabricated elements with 3-layer panels of spruce wood, which are perforated to improve the acoustics. The atmosphere of the multi-purpose hall is characterised by the warm colour of the wood. The new windows created interesting diagonal views and spatial references.

Construction Data

- 470m³ studs and laths

- External formwork

- Acoustic and lignature elements and wood fiber insulation. All Swiss wood.


Services of Timbatec

- SIA Phase 21 structural review

- SIA Phase 31 Preliminary design

- SIA Phase 32 Construction project

- SIA Phase 41 Tendering and comparison of offers

- SIA Phase 51 Implementation project

- SIA Phase 52 Execution

- SIA Phase 53 Commissioning

Client
Armasuisse Immobilier
1006 Lausanne


Architect
LZA Architectes SA
1700 Fribourg


Timber construction engineer
Timbatec Holzbauingenieure (Schweiz) AG Bern
3012 Bern


Timber construction
Gutknecht Holzbau AG
3280 Murten