The project
The Bäumlihof Gymnasium offers space for around 1500 students. About forty years after its opening, a complete renovation was due. During the extensive renovation measures, the electrical, sanitary and heating systems were replaced, the buildings were structurally strengthened and brought up to date from an energy point of view. For this purpose, the old concrete facade was completely dismantled and replaced by a wooden construction. The outer layer was installed on top of this. A new filigree façade made of thin glass-fiber-reinforced concrete panels now envelops the building. Furthermore, the wooden structure supports the large-format wood-aluminum windows with their opening casements. Timbatec Holzbauingenieure Schweiz AG planned the façade replacement and managed this sub-project.
The construction
The spruce wood construction is not simply the basis for the facade. Since wood only chars slowly in the event of a fire and still has a load-bearing and insulating effect with its residual cross-section, it is also the fire protection layer for the steel parts underneath.
The challenge
The challenge in designing the facade was to use the wooden elements to compensate for the unevenness and tolerances of the concrete structure. Steel elements were able to accommodate these tolerances and the punched-through concrete slabs.
Construction Data
- Structural timber FI/TA
Construction costs
- Construction costs 105 million francs
- Construction costs BKP 214 1.28 million francs
Services of Timbatec
- Planning of the facade with:
- Preliminary project
- construction project
- Devising/tendering
- Construction management and controls
Timberconstruction engineer
Timbatec Holzbauingenieure Schweiz AG
Timber constructioncontractor
Beer Holzbau AG
3072 Ostermundigen
Client
Canton Basel-Stadt
4058 Basel
Architecture
Enzmann Fischer Partner AG
8003 Zurich
General contracting
Zwimpfer Partner Architekten AG
8047 Zurich
Facade planning
Fiorio Fassadentechnik
9524 Zuzwil